Salt River Project (EIA ID 16572, AZ) serves 1,074,095 customers at 13.98 c/kWh (-1.28 c/kWh vs Arizona average) with 65.7 min/yr SAIDI (1.09 hrs/yr) with 63,437 net-metered residential solar systems (5.91% customer adoption). All figures reconcile directly against federal energy archives, state electrical licensing boards, California Energy Commission datasheets, and National Electrical Code engineering constants.

EIA Utility ID
16572
Res. Rate
13.98 c/kWh
SAIDI (All Events)
65.7 min/yr
Net-Metered PV
63,437 systems
Electric utility distribution substation transformers, ceramic insulators, and overhead feeder lines at dusk
Electric utility distribution substation transformers, ceramic insulators, and overhead feeder lines at dusk

How Does Salt River Project Compare on Tariffs and Reliability?

How Salt River Project (Political Subdivision) performs across 3 counties on kWh rates and outage resilience. Compare thermal ratings, overcurrent protection caps, and continuous load headroom carefully before expanding an existing home service panel.

Salt River Project (Political Subdivision) recorded 65.7 SAIDI outage minutes (1.09 hrs/yr, rank #149 of 751 reporting utilities). Typical residential meters drew 1,142.8 kWh/mo ($159.71/mo) in 2025, while its tariff bills residential power at 13.98 c/kWh (-1.28 c/kWh vs Arizona average vs. Arizona), offsetting ~$1,510/yr on an 8 kW array—compare rates directly with Arizona Public Service Co (17.03 c/kWh).

Where Does Salt River Project Sit Across US Utility Rates?

National utility tariff curve marking Salt River Project at 13.98 c/kWh vs. 18.54 c/kWh US mean.

Salt River Project Residential Tariff vs 1,989 US UtilitiesPositions Salt River Project's 13.98 c/kWh rate across reporting EIA-861 utilities. 3-6 c/kWh: 11 entries36-10 c/kWh: 100 entries10-13 c/kWh: 501 entries13-16 c/kWh: 808 entries1316-19 c/kWh: 320 entries19-23 c/kWh: 115 entries23-26 c/kWh: 60 entries2326-29 c/kWh: 27 entries29-32 c/kWh: 20 entries32-36 c/kWh: 7 entries3236-39 c/kWh: 6 entries39-42 c/kWh: 10 entries39Median 18.5 c/kWhSalt River Project: 13.98 c

How Does Salt River Project Rank Across Cost & Reliability?

Relative ranking of Salt River Project on residential electricity pricing and annual IEEE SAIDI outage duration. Regional housing vintage, storm hazard frequency, and wholesale utility prices directly govern residential upgrade payback across jurisdictions.

Salt River Project Grid & Tariff BenchmarksShows where Salt River Project ranks on residential rate, SAIDI, and storm exposure. 0% (Low)50% Median100% (Top)Residential Rate13.98 c/kWhAnnual SAIDI65.7 min/yrMajor-Storm Share24.0%

What Do EIA-861 Benchmarks Show for Salt River Project?

Tariff rank, outage reliability metrics, and 2026 Post-25D solar payback figures for Salt River Project in Arizona. Data intervals combine current 2025 federal utility and BLS wage releases with verified state electrical board rosters.

Lowest Rate #970 / 1,989

13.98 c/kWh (-1.28 vs AZ)

Commercial avg: 10.85 c/kWh; Industrial: 8.36 c/kWh; est. residential bill $159.71/mo.

Reliability #149 / 751

65.7 min/yr (1.09 hrs)

24.0% (15.8 min) from Major Event Days; avg restore 64.6 min (~1.9 kWh @ 1.8 kW).

Post-25D Payback

15.6 Years @ 13.98 c/kWh

8 kW cash system ($23,600 at $2.95/W, 0% 25D) offsets ~$1,510/yr at 1,350 kWh/kW.

Distributed PV

63,437 Net-Metered Systems

435.41 MW residential PV (5.91% of customers) across 3 counties; state FEMA declarations (2015-2026): 43.

Salt River Project Reliability & Solar Offset Calculation

Backup_Energy = (64.6 min / 60) * 1.8 kW = 1.9 kWh/event | Solar_Offset = 10,800 kWh * $0.1398 = $1,510/yr

EIA-861 2025 Utility ID 16572: Rate=13.98 c/kWh, Cust=1,074,095, SAIDI=65.7 min, PV=63,437.

Result: 1.09 outage hrs/yr; 15.6 yr 8 kW cash payback (0% 25D).

What Are the EIA-861 Filing Metrics for Salt River Project?

Verified customer accounts, residential and commercial tariffs, and net-metering totals filed by Salt River Project. Inspect manufacturer nameplate documentation, UL listing boundaries, and utility rate schedules closely before ordering electrical hardware.

Form EIA-861 2025 filing metrics for Salt River Project (Utility ID 16572).
EIA Utility ID & BA CodeID 16572 · SRP
State & Ownership TypeAZ · Political Subdivision
Retail Electricity Rates13.98 c/kWh Res · 10.85 c Comm · 8.36 c Ind
Avg Monthly Usage & Bill1,142.8 kWh/mo ($159.71/mo est.)
SAIDI (All Events w/ MED)65.7 min/yr (1.09 hrs/yr)
SAIDI (Without Major Events)49.9 min/yr (Storm share: 24.0%)
SAIFI & CAIDI (Per-Outage Avg)1.017 /yr · 64.6 min restore
Residential Net-Metered PV63,437 systems (435.41 MW)
Counties Served (Sample)3 counties (Gila, Maricopa, Pinal)

Which Peer Electric Utilities Operate in AZ?

Nearby Arizona electric utilities of comparable customer size led by Arizona Public Service Co (17.03 c/kWh). Review related calculators, peer benchmarks, and source citations below to validate design assumptions for your electrical service.

In-state EIA-861 peers ranked by customer base.
UtilityRes RateSAIDIRes PVCustomers
Arizona Public Service Co 17.03 c 73.1 min 190,456 1,287,097
Tucson Electric Power Co 14.88 c 41.8 min 54,718 416,268
UNS Electric, Inc 16.99 c 81.2 min 11,315 95,288
Trico Electric Cooperative Inc 14.26 c 90.0 min 5,956 53,721
What to Check & Best-Fit Scenarios

What Should Salt River Project Customers Check Beyond Historical EIA-861 Averages?

Form EIA-861 data for Salt River Project (Political Subdivision, AZ) summarizes annual utility filings—confirm active rate riders and feeder reliability at your meter.

  • ERCOT / retail choice note or local riders: confirm whether Salt River Project acts as a wires-only TDU or bundled utility in AZ.
  • Transformer limits: Salt River Project interconnection engineering still checks neighborhood transformer kVA regardless of 65.7 SAIDI.

Salt River Project Solar & Battery Evaluators

Compare your actual Salt River Project monthly kWh statement against 13.98 c/kWh and verify current export tariffs in AZ.

Salt River Project Outage & Generator Planners

Use Salt River Project's SAIDI history alongside NEC 705.12 120% busbar checks when sizing backup storage or transfer switches.

Which Homeowner Electrical & Solar Questions Come Up Most Often?

Answers for Salt River Project (Arizona) customers grounded in 2025 Form EIA-861 filings and NEC 705.12 rules. Cross-check local Authority Having Jurisdiction amendments and serving utility net-metering terms before finalizing project sizing.

What is Salt River Project's residential electricity rate and 2026 solar payback?

Salt River Project averages 13.98 c/kWh (-1.28 c/kWh vs Arizona average vs. Arizona). At 0% federal 25D credit in 2026, an 8 kW cash array offsets ~$1,510/yr (15.6-year payback).

How reliable is Salt River Project compared to peer Arizona utilities?

Salt River Project recorded 65.7 SAIDI outage minutes (1.09 hrs/yr, rank #149 of 751 reporting utilities); compare rates and outage history directly with Arizona Public Service Co (17.03 c/kWh) across Arizona.

Which counties and customers does Salt River Project serve in Arizona?

EIA-861 filings list 1,074,095 customers across 3 counties including Gila, Maricopa, Pinal, with 63,437 net-metered residential solar installations. Review current municipal Authority Having Jurisdiction (AHJ) code amendments affecting Salt River Project.

Sources

  1. Annual Electric Power Industry Report, Form EIA-861 (Reliability, Sales, Net Metering, Average Bill, Service Territory) — U.S. Energy Information Administration (EIA), 2025 Release (f8612025) (retrieved 2026-11-23)
  2. NFPA 70 National Electrical Code (Section Numbers & Standard Engineering Tables Only) — National Fire Protection Association (NFPA), 2020 / 2023 / 2026 Editions (retrieved 2026-11-23)
  3. Residential Clean Energy Credit (IRC Section 25D — Terminated After Dec. 31, 2025) — Internal Revenue Service (IRS), 2026 Guidance (P.L. 119-21) (retrieved 2026-11-23)

Which Regional Electrical & Panel Upgrade Metros Compare Closest?

Check Wiring & Solar Numbers Before Getting Quotes

Verify panel capacity for solar, electrical box space, proper wire gauge for EV chargers, and 2026 home solar payback using local utility rates.

Verify State-Licensed Electricians & Safety Recalls

Look up active state electrician licenses (TX, WA, CO, OR, DE), check local power-outage history, and inspect federal product recall notices.