title: "Columbia Rural Elec Assn, Inc (WA) Rate & SAIDI"
url: https://epri-peac.com/utilities/wa-columbia-rural-elec-assn-inc-4041/
description: "2025 EIA-861 profile for Columbia Rural Elec Assn, Inc (WA): 15.59 c/kWh rate, SAIDI 200.2 min/yr, 206 solar systems. Source-verified US engineering data."
---

EIA-861 Grid Reliability & Net Metering

# Columbia Rural Elec Assn, Inc (WA) — Grid Reliability & Solar Data

Filing: **Form EIA-861 (2025 Release)** Verified: **2026-11-26**

Columbia Rural Elec Assn, Inc (EIA ID 4041, WA) serves 4,466 customers at 15.59 c/kWh (+2.42 c/kWh vs Washington average) with 200.2 min/yr SAIDI (3.34 hrs/yr) with 206 net-metered residential solar systems (4.61% customer adoption). All figures reconcile directly against federal energy archives, state electrical licensing boards, California Energy Commission datasheets, and National Electrical Code engineering constants.

- **EIA Utility ID** : 4041

- **Res. Rate** : 15.59 c/kWh

- **SAIDI (All Events)** : 200.2 min/yr

- **Net-Metered PV** : 206 systems

Electric utility distribution substation transformers, ceramic insulators, and overhead feeder lines at dusk

## How Does Columbia Rural Elec Assn, Inc Compare on Tariffs and Reliability?

How Columbia Rural Elec Assn, Inc (Cooperative) performs across 2 counties on kWh rates and outage resilience. Data intervals combine current 2025 federal utility and BLS wage releases with verified state electrical board rosters.

Columbia Rural Elec Assn, Inc (Cooperative) recorded 200.2 SAIDI outage minutes (3.34 hrs/yr, rank #420 of 751 reporting utilities). Typical residential meters drew 1,123.4 kWh/mo ($175.08/mo) in 2025, while its tariff bills residential power at 15.59 c/kWh (+2.42 c/kWh vs Washington average vs. Washington), offsetting ~$1,684/yr on an 8 kW array—compare rates directly with Big Bend Electric Coop, Inc (9.61 c/kWh).

## Where Does Columbia Rural Elec Assn, Inc Sit Across US Utility Rates?

National utility tariff curve marking Columbia Rural Elec Assn, Inc at 15.59 c/kWh vs. 18.54 c/kWh US mean.

## How Does Columbia Rural Elec Assn, Inc Rank Across Cost & Reliability?

Relative ranking of Columbia Rural Elec Assn, Inc on residential electricity pricing and annual IEEE SAIDI outage duration.

## What Do EIA-861 Benchmarks Show for Columbia Rural Elec Assn, Inc?

Tariff rank, outage reliability metrics, and 2026 Post-25D solar payback figures for Columbia Rural Elec Assn, Inc in Washington.

Lowest Rate #1,333 / 1,989

### 15.59 c/kWh (+2.42 vs WA)

Commercial avg: 8.32 c/kWh; Industrial: 9.55 c/kWh; est. residential bill $175.08/mo.

Reliability #420 / 751

### 200.2 min/yr (3.34 hrs)

21.3% (42.7 min) from Major Event Days; avg restore 129.2 min (~3.9 kWh @ 1.8 kW).

Post-25D Payback

### 14.0 Years @ 15.59 c/kWh

8 kW cash system ($23,600 at $2.95/W, 0% 25D) offsets ~$1,684/yr at 1,350 kWh/kW.

Distributed PV

### 206 Net-Metered Systems

1.888 MW residential PV (4.61% of customers) across 2 counties; state FEMA declarations (2015-2026): 96.

Columbia Rural Elec Assn, Inc Reliability & Solar Offset Calculation

Backup_Energy = (129.2 min / 60) * 1.8 kW = 3.9 kWh/event | Solar_Offset = 10,800 kWh * $0.1559 = $1,684/yr

EIA-861 2025 Utility ID 4041: Rate=15.59 c/kWh, Cust=4,466, SAIDI=200.2 min, PV=206.

**Result:** 3.34 outage hrs/yr; 14.0 yr 8 kW cash payback (0% 25D).

## What Are the EIA-861 Filing Metrics for Columbia Rural Elec Assn, Inc?

Verified customer accounts, residential and commercial tariffs, and net-metering totals filed by Columbia Rural Elec Assn, Inc. All figures trace directly to published federal energy filings, state electrical boards, CEC datasheets, and NFPA 70 NEC tables.

Form EIA-861 2025 filing metrics for Columbia Rural Elec Assn, Inc (Utility ID 4041).

| EIA Utility ID & BA Code | ID 4041 · BPAT |
|---|---|
| State & Ownership Type | WA · Cooperative |
| Retail Electricity Rates | 15.59 c/kWh Res · 8.32 c Comm · 9.55 c Ind |
| Avg Monthly Usage & Bill | 1,123.4 kWh/mo ($175.08/mo est.) |
| SAIDI (All Events w/ MED) | 200.2 min/yr (3.34 hrs/yr) |
| SAIDI (Without Major Events) | 157.5 min/yr (Storm share: 21.3%) |
| SAIFI & CAIDI (Per-Outage Avg) | 1.55 /yr · 129.2 min restore |
| Residential Net-Metered PV | 206 systems (1.888 MW) |
| Counties Served (Sample) | 2 counties (Columbia, Walla Walla) |

## Which Peer Electric Utilities Operate in WA?

Nearby Washington electric utilities of comparable customer size led by Big Bend Electric Coop, Inc (9.61 c/kWh).

In-state EIA-861 peers ranked by customer base.

| Utility | Res Rate | SAIDI | Res PV | Customers |
|---|---|---|---|---|
| [**Big Bend Electric Coop, Inc**](https://epri-peac.com/utilities/wa-big-bend-electric-coop-inc-1723/) | 9.61 c | 448.9 min | 115 | 6,365 |
| [**Lakeview Light & Power**](https://epri-peac.com/utilities/wa-lakeview-light-power-10627/) | 10.87 c | — | 22 | 8,341 |
| [**Tesla Inc.**](https://epri-peac.com/utilities/wa-tesla-inc-57313/) | 4.71 c | — | 0 | 99 |
| [**Kootenai Electric Cooperative**](https://epri-peac.com/utilities/wa-kootenai-electric-cooperative-10454/) | 12.11 c | — | 0 | 93 |

What to Check & Best-Fit Scenarios

## What Should Columbia Rural Elec Assn, Inc Customers Check Beyond Historical EIA-861 Averages?

Form EIA-861 data for Columbia Rural Elec Assn, Inc (Cooperative, WA) summarizes annual utility filings—confirm active rate riders and feeder reliability at your meter.

- Annual snapshot caveat: Columbia Rural Elec Assn, Inc (Cooperative) reports historical 2025 EIA-861 averages rather than live rate-case riders in WA.
- Export credit rules: check Columbia Rural Elec Assn, Inc's active net-billing or avoided-cost schedule before assuming 1-to-1 retail solar offset.

### Columbia Rural Elec Assn, Inc Solar & Battery Evaluators

Compare your actual Columbia Rural Elec Assn, Inc monthly kWh statement against 15.59 c/kWh and verify current export tariffs in WA.

### Columbia Rural Elec Assn, Inc Outage & Generator Planners

Use Columbia Rural Elec Assn, Inc's SAIDI history alongside NEC 705.12 120% busbar checks when sizing backup storage or transfer switches.

## Which Homeowner Electrical & Solar Questions Come Up Most Often?

Answers for Columbia Rural Elec Assn, Inc (Washington) customers grounded in 2025 Form EIA-861 filings and NEC 705.12 rules.

### What is Columbia Rural Elec Assn, Inc's residential electricity rate and 2026 solar payback?

Columbia Rural Elec Assn, Inc averages 15.59 c/kWh (+2.42 c/kWh vs Washington average vs. Washington). At 0% federal 25D credit in 2026, an 8 kW cash array offsets ~$1,684/yr (14.0-year payback).

### How reliable is Columbia Rural Elec Assn, Inc compared to peer Washington utilities?

Columbia Rural Elec Assn, Inc recorded 200.2 SAIDI outage minutes (3.34 hrs/yr, rank #420 of 751 reporting utilities); compare rates and outage history directly with Big Bend Electric Coop, Inc (9.61 c/kWh) across Washington.

### Which counties and customers does Columbia Rural Elec Assn, Inc serve in Washington?

EIA-861 filings list 4,466 customers across 2 counties including Columbia, Walla Walla, with 206 net-metered residential solar installations. Review current municipal Authority Having Jurisdiction (AHJ) code amendments affecting Columbia Rural Elec Assn, Inc.

## Related Pages

Explore Washington energy benchmarks, Big Bend Electric Coop, Inc, county outage profiles, and NEC 705.12 tools alongside Columbia Rural Elec Assn, Inc.

[Washington State Energy Rates & Utilities](https://epri-peac.com/states/washington/) [All Washington County Power & Outage Profiles](https://epri-peac.com/counties/washington/) [Check Solar 120% Busbar Rule (NEC 705.12)](https://epri-peac.com/tools/solar-busbar-120/) [All Indexed US Electric Utilities](https://epri-peac.com/utilities/)

## Sources

1. [Annual Electric Power Industry Report, Form EIA-861 (Reliability, Sales, Net Metering, Average Bill, Service Territory)](https://www.eia.gov/electricity/data/eia861/) — U.S. Energy Information Administration (EIA), 2025 Release (f8612025) (retrieved 2026-11-23)
2. [NFPA 70 National Electrical Code (Section Numbers & Standard Engineering Tables Only)](https://www.nfpa.org/codes-and-standards/nfpa-70-standard-development/70) — National Fire Protection Association (NFPA), 2020 / 2023 / 2026 Editions (retrieved 2026-11-23)
3. [Residential Clean Energy Credit (IRC Section 25D — Terminated After Dec. 31, 2025)](https://www.irs.gov/credits-deductions/residential-clean-energy-credit) — Internal Revenue Service (IRS), 2026 Guidance (P.L. 119-21) (retrieved 2026-11-23)

Solar & Backup Calculators

Evaluate 60 A hybrid battery ESS backfeed limits (NEC 705.12) and 2026 solar payback using 15.59 c/kWh rates.
[Check 120% Busbar Rule](https://epri-peac.com/tools/solar-busbar-120/) [View Battery & Generator Specs](https://epri-peac.com/ev-chargers/)