# Southwestern Public Service Co (TX) — Grid Reliability & Solar Data

Filing: **Form EIA-861 (2025 Release)** Verified: **2026-11-26**

Southwestern Public Service Co (EIA ID 17718, TX) serves 223,685 customers at 13.94 c/kWh (-1.46 c/kWh vs Texas average) with 441.4 min/yr SAIDI (7.36 hrs/yr) with zero residential net-metered PV reported in 2025 filings. All figures reconcile directly against federal energy archives, state electrical licensing boards, California Energy Commission datasheets, and National Electrical Code engineering constants.

- **EIA Utility ID** : 17718

- **Res. Rate** : 13.94 c/kWh

- **SAIDI (All Events)** : 441.4 min/yr

- **Net-Metered PV** : Unreported

Electric utility distribution substation transformers, ceramic insulators, and overhead feeder lines at dusk

## How Does Southwestern Public Service Co Compare on Tariffs and Reliability?

EIA-861 rate delta (-1.46 c/kWh vs Texas average), customer scale (223,685), and 2026 solar payback benchmarks for Southwestern Public Service Co.

Serving 223,685 customers across 45 counties including Andrews, Armstrong, Bailey in Texas, Southwestern Public Service Co (Investor Owned, Balancing Authority SWPP) bills residential power at 13.94 c/kWh (-1.46 c/kWh vs Texas average vs. Texas), offsetting ~$1,506/yr on an 8 kW array. Grid filings show the utility logged 441.4 SAIDI outage minutes (7.36 hrs/yr, 65.7% storm-driven), making battery backup or a standby ATS worthwhile, with zero residential net-metered PV reported in 2025 filings.

## Where Does Southwestern Public Service Co Sit Across US Utility Rates?

Positions Southwestern Public Service Co (13.94 c/kWh) across 1,989 US electric utility residential tariffs. Review related calculators, peer benchmarks, and source citations below to validate design assumptions for your electrical service.

## How Does Southwestern Public Service Co Rank Across Cost & Reliability?

Percentile placement of Southwestern Public Service Co across retail kWh electricity cost and IEEE grid reliability outage metrics.

## What Do EIA-861 Benchmarks Show for Southwestern Public Service Co?

Four key EIA-861 rate, outage, and solar payback benchmarks for Southwestern Public Service Co (Investor Owned) in Texas.

Lowest Rate #952 / 1,989

### 13.94 c/kWh (-1.46 vs TX)

Commercial avg: 9.67 c/kWh; Industrial: 5.04 c/kWh; est. residential bill $130.54/mo.

Reliability #610 / 751

### 441.4 min/yr (7.36 hrs)

65.7% (290.2 min) from Major Event Days; avg restore 258.1 min (~7.7 kWh @ 1.8 kW).

Post-25D Payback

### 15.7 Years @ 13.94 c/kWh

8 kW cash system ($23,600 at $2.95/W, 0% 25D) offsets ~$1,506/yr at 1,350 kWh/kW.

Service Territory

### 223,685 Customers · 45 Counties

Serves 45 counties including Andrews, Armstrong, Bailey in Texas; state FEMA declarations (2015-2026): 56.

Southwestern Public Service Co Reliability & Solar Offset Calculation

Backup_Energy = (258.1 min / 60) * 1.8 kW = 7.7 kWh/event | Solar_Offset = 10,800 kWh * $0.1394 = $1,506/yr

EIA-861 2025 Utility ID 17718: Rate=13.94 c/kWh, Cust=223,685, SAIDI=441.4 min.

**Result:** 7.36 outage hrs/yr; 15.7 yr 8 kW cash payback (0% 25D).

## What Are the EIA-861 Filing Metrics for Southwestern Public Service Co?

Complete Form EIA-861 filing summary for Southwestern Public Service Co (ID 17718) covering sales, PV, and counties. Published percentiles compare local state, county, metro, and certified equipment metrics against nationwide residential electrical baselines.

Form EIA-861 2025 filing metrics for Southwestern Public Service Co (Utility ID 17718).

| EIA Utility ID & BA Code | ID 17718 · SWPP |
|---|---|
| State & Ownership Type | TX · Investor Owned |
| Retail Electricity Rates | 13.94 c/kWh Res · 9.67 c Comm · 5.04 c Ind |
| Avg Monthly Usage & Bill | 936.6 kWh/mo ($130.54/mo est.) |
| SAIDI (All Events w/ MED) | 441.4 min/yr (7.36 hrs/yr) |
| SAIDI (Without Major Events) | 151.2 min/yr (Storm share: 65.7%) |
| SAIFI & CAIDI (Per-Outage Avg) | 1.71 /yr · 258.1 min restore |
| Residential Net-Metered PV | Not reported in 2025 EIA-861 |
| Counties Served (Sample) | 45 counties (Andrews, Armstrong, Bailey, Borden, Briscoe, Carson, Castro, Cochran, Cottle, Crosby) |

## Which Peer Electric Utilities Operate in TX?

Compare Southwestern Public Service Co directly with AEP Texas North Company and nearby Texas electric utilities by customer base.

In-state EIA-861 peers ranked by customer base.

| Utility | Res Rate | SAIDI | Res PV | Customers |
|---|---|---|---|---|
| [**AEP Texas North Company**](https://epri-peac.com/utilities/tx-aep-texas-north-company-20404/) | TDU | 133.0 min | 0 | 200,476 |
| [**Southwestern Electric Power Co**](https://epri-peac.com/utilities/tx-southwestern-electric-power-co-17698/) | 12.6 c | 467.1 min | 0 | 157,119 |
| [**Denton County Elec Coop, Inc**](https://epri-peac.com/utilities/tx-denton-county-elec-coop-inc-5078/) | 13.18 c | 49.4 min | 9,170 | 310,805 |
| [**Magic Valley Electric Coop Inc**](https://epri-peac.com/utilities/tx-magic-valley-electric-coop-inc-11501/) | 10.51 c | 288.5 min | 1,961 | 129,596 |

What to Check & Best-Fit Scenarios

## What Should Southwestern Public Service Co Customers Check Beyond Historical EIA-861 Averages?

Form EIA-861 data for Southwestern Public Service Co (Investor Owned, TX) summarizes annual utility filings—confirm active rate riders and feeder reliability at your meter.

- Not a substitute for meter bills: tiered and seasonal kWh blocks inside Southwestern Public Service Co (TX) shift real bills away from 13.94 c/kWh.
- Outage clustering: Major Event Days skew Southwestern Public Service Co annual minutes differently than routine non-storm reliability.

### Southwestern Public Service Co Solar & Battery Evaluators

Compare your actual Southwestern Public Service Co monthly kWh statement against 13.94 c/kWh and verify current export tariffs in TX.

### Southwestern Public Service Co Outage & Generator Planners

Use Southwestern Public Service Co's SAIDI history alongside NEC 705.12 120% busbar checks when sizing backup storage or transfer switches.

## Which Homeowner Electrical & Solar Questions Come Up Most Often?

Answers for Southwestern Public Service Co (Texas) customers grounded in 2025 Form EIA-861 filings and NEC 705.12 rules.

### What is Southwestern Public Service Co's residential electricity rate and 2026 solar payback?

Southwestern Public Service Co averages 13.94 c/kWh (-1.46 c/kWh vs Texas average vs. Texas). At 0% federal 25D credit in 2026, an 8 kW cash array offsets ~$1,506/yr (15.7-year payback).

### How reliable is Southwestern Public Service Co compared to peer Texas utilities?

Southwestern Public Service Co logged 441.4 SAIDI outage minutes (7.36 hrs/yr, 65.7% storm-driven), making battery backup or a standby ATS worthwhile; compare rates and outage history directly with AEP Texas North Company (15.4 c/kWh) across Texas.

### Which counties and customers does Southwestern Public Service Co serve in Texas?

EIA-861 filings list 223,685 customers across 45 counties including Andrews, Armstrong, Bailey, with 0 net-metered residential solar installations. Review current municipal Authority Having Jurisdiction (AHJ) code amendments affecting Southwestern Public Service Co.

## Related Pages

Explore Texas energy benchmarks, AEP Texas North Company, county outage profiles, and NEC 705.12 tools alongside Southwestern Public Service Co.

[Texas State Energy Rates & Utilities](https://epri-peac.com/states/texas/) [All Texas County Power & Outage Profiles](https://epri-peac.com/counties/texas/) [Check Solar 120% Busbar Rule (NEC 705.12)](https://epri-peac.com/tools/solar-busbar-120/) [All Indexed US Electric Utilities](https://epri-peac.com/utilities/)

## Sources

1. [Annual Electric Power Industry Report, Form EIA-861 (Reliability, Sales, Net Metering, Average Bill, Service Territory)](https://www.eia.gov/electricity/data/eia861/) — U.S. Energy Information Administration (EIA), 2025 Release (f8612025) (retrieved 2026-11-23)
2. [NFPA 70 National Electrical Code (Section Numbers & Standard Engineering Tables Only)](https://www.nfpa.org/codes-and-standards/nfpa-70-standard-development/70) — National Fire Protection Association (NFPA), 2020 / 2023 / 2026 Editions (retrieved 2026-11-23)
3. [Residential Clean Energy Credit (IRC Section 25D — Terminated After Dec. 31, 2025)](https://www.irs.gov/credits-deductions/residential-clean-energy-credit) — Internal Revenue Service (IRS), 2026 Guidance (P.L. 119-21) (retrieved 2026-11-23)

Solar & Backup Calculators

Evaluate 60 A hybrid battery ESS backfeed limits (NEC 705.12) and 2026 solar payback using 13.94 c/kWh rates.
[Check 120% Busbar Rule](https://epri-peac.com/tools/solar-busbar-120/) [View Battery & Generator Specs](https://epri-peac.com/ev-chargers/)