EIA-861 Grid Reliability & Net Metering

# City of Amory (MS) — Grid Reliability & Solar Data

Filing: **Form EIA-861 (2025 Release)** Verified: **2026-11-26**

City of Amory (EIA ID 571, MS) serves 2,836 customers at 12.31 c/kWh (-1.72 c/kWh vs Mississippi average) with no standalone IEEE SAIDI filing (1 county served) with zero residential net-metered PV reported in 2025 filings. All figures reconcile directly against federal energy archives, state electrical licensing boards, California Energy Commission datasheets, and National Electrical Code engineering constants.

- **EIA Utility ID** : 571

- **Res. Rate** : 12.31 c/kWh

- **SAIDI (All Events)** : Not reported in EIA-861

- **Net-Metered PV** : Unreported

Electric utility distribution substation transformers, ceramic insulators, and overhead feeder lines at dusk

## How Does City of Amory Compare on Tariffs and Reliability?

EIA-861 rate delta (-1.72 c/kWh vs Mississippi average), customer scale (2,836), and 2026 solar payback benchmarks for City of Amory.

Ranked #466 of 1,989 reporting US utilities for residential rate (top 23.6%; lower than 76.4% of peers), City of Amory serves 2,836 accounts in Mississippi (Municipal). Commercial power averages 13.33 c/kWh. It did not file standalone IEEE SAIDI metrics in 2025 EIA-861 (state customer-weighted SAIDI is 524.4 min/yr), with zero residential net-metered PV reported in 2025 filings.

## Where Does City of Amory Sit Across US Utility Rates?

Positions City of Amory (12.31 c/kWh) across 1,989 US electric utility residential tariffs. Cross-check local Authority Having Jurisdiction amendments and serving utility net-metering terms before finalizing project sizing.

## How Does City of Amory Rank Across Cost & Reliability?

Percentile placement of City of Amory across retail kWh electricity cost and IEEE grid reliability outage metrics. Data intervals combine current 2025 federal utility and BLS wage releases with verified state electrical board rosters.

## What Do EIA-861 Benchmarks Show for City of Amory?

Four key EIA-861 rate, outage, and solar payback benchmarks for City of Amory (Municipal) in Mississippi. Every reported metric links directly to federal public records or state regulatory filings with zero paid contractor placements.

Lowest Rate #466 / 1,989

### 12.31 c/kWh (-1.72 vs MS)

Commercial avg: 13.33 c/kWh; Industrial: 8.69 c/kWh; est. residential bill $136.31/mo.

State Reliability Context

### 524.4 min/yr (MS Avg)

Utility did not file separate IEEE SAIDI in 2025; Mississippi customer-weighted SAIDI is 524.4 min/yr.

Post-25D Payback

### 17.8 Years @ 12.31 c/kWh

8 kW cash system ($23,600 at $2.95/W, 0% 25D) offsets ~$1,329/yr at 1,350 kWh/kW.

Service Territory

### 2,836 Customers · 1 County

Serves 1 county including Monroe in Mississippi; state FEMA declarations (2015-2026): 34.

City of Amory Reliability & Solar Offset Calculation

Backup_Energy = (120.0 min / 60) * 1.8 kW = 3.6 kWh/event | Solar_Offset = 10,800 kWh * $0.1231 = $1,329/yr

EIA-861 2025 Utility ID 571: Rate=12.31 c/kWh, Cust=2,836.

**Result:** 17.8 yr 8 kW cash payback at 12.31 c/kWh (0% 25D).

## What Are the EIA-861 Filing Metrics for City of Amory?

Complete Form EIA-861 filing summary for City of Amory (ID 571) covering sales, PV, and counties. Use these verified dataset benchmarks alongside a licensed electrician load calculation to compare residential upgrade bids with confidence.

Form EIA-861 2025 filing metrics for City of Amory (Utility ID 571).

| EIA Utility ID & BA Code | ID 571 · TVA |
|---|---|
| State & Ownership Type | MS · Municipal |
| Retail Electricity Rates | 12.31 c/kWh Res · 13.33 c Comm · 8.69 c Ind |
| Avg Monthly Usage & Bill | 1,107.1 kWh/mo ($136.31/mo est.) |
| Residential Net-Metered PV | Not reported in 2025 EIA-861 |
| Counties Served (Sample) | 1 county (Monroe) |

## Which Peer Electric Utilities Operate in MS?

Compare City of Amory directly with City of West Point - (MS) and nearby Mississippi electric utilities by customer base.

In-state EIA-861 peers ranked by customer base.

| Utility | Res Rate | SAIDI | Res PV | Customers |
|---|---|---|---|---|
| [**City of West Point - (MS)**](https://epri-peac.com/utilities/ms-city-of-west-point-ms-20394/) | 12.88 c | — | 0 | 2,987 |
| [**City of Philadelphia - (MS)**](https://epri-peac.com/utilities/ms-city-of-philadelphia-ms-14947/) | 12.57 c | — | 0 | 2,669 |
| [**City of Aberdeen - (MS)**](https://epri-peac.com/utilities/ms-city-of-aberdeen-ms-55/) | 13.19 c | — | 0 | 2,577 |
| [**Louisville Electric System**](https://epri-peac.com/utilities/ms-louisville-electric-system-11247/) | 11.5 c | — | 0 | 2,447 |

What to Check & Best-Fit Scenarios

## What Should City of Amory Customers Check Beyond Historical EIA-861 Averages?

Form EIA-861 data for City of Amory (Municipal, MS) summarizes annual utility filings—confirm active rate riders and feeder reliability at your meter.

- ERCOT / retail choice note or local riders: confirm whether City of Amory acts as a wires-only TDU or bundled utility in MS.
- Transformer limits: City of Amory interconnection engineering still checks neighborhood transformer kVA regardless of reported SAIDI.

### City of Amory Solar & Battery Evaluators

Compare your actual City of Amory monthly kWh statement against 12.31 c/kWh and verify current export tariffs in MS.

### City of Amory Outage & Generator Planners

Use City of Amory's SAIDI history alongside NEC 705.12 120% busbar checks when sizing backup storage or transfer switches.

## Which Homeowner Electrical & Solar Questions Come Up Most Often?

Answers for City of Amory (Mississippi) customers grounded in 2025 Form EIA-861 filings and NEC 705.12 rules. Published percentiles compare local state, county, metro, and certified equipment metrics against nationwide residential electrical baselines.

### What is City of Amory's residential electricity rate and 2026 solar payback?

City of Amory averages 12.31 c/kWh (-1.72 c/kWh vs Mississippi average vs. Mississippi). At 0% federal 25D credit in 2026, an 8 kW cash array offsets ~$1,329/yr (17.8-year payback).

### How reliable is City of Amory compared to peer Mississippi utilities?

City of Amory did not file standalone IEEE SAIDI metrics in 2025 EIA-861 (state customer-weighted SAIDI is 524.4 min/yr); compare rates and outage history directly with City of West Point - (MS) (12.88 c/kWh) across Mississippi.

### Which counties and customers does City of Amory serve in Mississippi?

EIA-861 filings list 2,836 customers across 1 county including Monroe, with 0 net-metered residential solar installations. Review current municipal Authority Having Jurisdiction (AHJ) code amendments affecting City of Amory.

## Related Pages

Explore Mississippi energy benchmarks, City of West Point - (MS), county outage profiles, and NEC 705.12 tools alongside City of Amory.

[Mississippi State Energy Rates & Utilities](https://epri-peac.com/states/mississippi/) [All Mississippi County Power & Outage Profiles](https://epri-peac.com/counties/mississippi/) [Check Solar 120% Busbar Rule (NEC 705.12)](https://epri-peac.com/tools/solar-busbar-120/) [All Indexed US Electric Utilities](https://epri-peac.com/utilities/)

## Sources

1. [Annual Electric Power Industry Report, Form EIA-861 (Reliability, Sales, Net Metering, Average Bill, Service Territory)](https://www.eia.gov/electricity/data/eia861/) — U.S. Energy Information Administration (EIA), 2025 Release (f8612025) (retrieved 2026-11-23)
2. [NFPA 70 National Electrical Code (Section Numbers & Standard Engineering Tables Only)](https://www.nfpa.org/codes-and-standards/nfpa-70-standard-development/70) — National Fire Protection Association (NFPA), 2020 / 2023 / 2026 Editions (retrieved 2026-11-23)
3. [Residential Clean Energy Credit (IRC Section 25D — Terminated After Dec. 31, 2025)](https://www.irs.gov/credits-deductions/residential-clean-energy-credit) — Internal Revenue Service (IRS), 2026 Guidance (P.L. 119-21) (retrieved 2026-11-23)

Solar & Backup Calculators

Evaluate 60 A hybrid battery ESS backfeed limits (NEC 705.12) and 2026 solar payback using 12.31 c/kWh rates.
[Check 120% Busbar Rule](https://epri-peac.com/tools/solar-busbar-120/) [View Battery & Generator Specs](https://epri-peac.com/ev-chargers/)