title: "The Potomac Edison Company (MD) Rate & SAIDI"
url: https://epri-peac.com/utilities/md-the-potomac-edison-company-15263/
description: "2025 EIA-861 profile for The Potomac Edison Company (MD): 15.14 c/kWh rate, SAIDI 399.1 min/yr, 8,752 solar systems. Source-verified US engineering data."
---

EIA-861 Grid Reliability & Net Metering

# The Potomac Edison Company (MD) — Grid Reliability & Solar Data

Filing: **Form EIA-861 (2025 Release)** Verified: **2026-11-26**

The Potomac Edison Company (EIA ID 15263, MD) serves 252,583 customers at 15.14 c/kWh (-4.39 c/kWh vs Maryland average) with 399.1 min/yr SAIDI (6.65 hrs/yr) with 8,752 net-metered residential solar systems (3.46% customer adoption). All figures reconcile directly against federal energy archives, state electrical licensing boards, California Energy Commission datasheets, and National Electrical Code engineering constants.

- **EIA Utility ID** : 15263

- **Res. Rate** : 15.14 c/kWh

- **SAIDI (All Events)** : 399.1 min/yr

- **Net-Metered PV** : 8,752 systems

Electric utility distribution substation transformers, ceramic insulators, and overhead feeder lines at dusk

## How Does The Potomac Edison Company Compare on Tariffs and Reliability?

EIA-861 rate delta (-4.39 c/kWh vs Maryland average), customer scale (252,583), and 2026 solar payback benchmarks for The Potomac Edison Company.

Serving 252,583 customers across 7 counties including Allegany, Carroll, Frederick in Maryland, The Potomac Edison Company (Investor Owned, Balancing Authority PJM) bills residential power at 15.14 c/kWh (-4.39 c/kWh vs Maryland average vs. Maryland), offsetting ~$1,635/yr on an 8 kW array. Grid filings show the utility logged 399.1 SAIDI outage minutes (6.65 hrs/yr, 56.5% storm-driven), making battery backup or a standby ATS worthwhile, with 8,752 net-metered residential solar systems (3.46% customer adoption).

## Where Does The Potomac Edison Company Sit Across US Utility Rates?

Positions The Potomac Edison Company (15.14 c/kWh) across 1,989 US electric utility residential tariffs. Published percentiles compare local state, county, metro, and certified equipment metrics against nationwide residential electrical baselines.

## How Does The Potomac Edison Company Rank Across Cost & Reliability?

Percentile placement of The Potomac Edison Company across retail kWh electricity cost and IEEE grid reliability outage metrics.

## What Do EIA-861 Benchmarks Show for The Potomac Edison Company?

Four key EIA-861 rate, outage, and solar payback benchmarks for The Potomac Edison Company (Investor Owned) in Maryland.

Lowest Rate #1,245 / 1,989

### 15.14 c/kWh (-4.39 vs MD)

Commercial avg: 7.76 c/kWh; Industrial: 4.03 c/kWh; est. residential bill $173.26/mo.

Reliability #591 / 751

### 399.1 min/yr (6.65 hrs)

56.5% (225.3 min) from Major Event Days; avg restore 307.5 min (~9.2 kWh @ 1.8 kW).

Post-25D Payback

### 14.4 Years @ 15.14 c/kWh

8 kW cash system ($23,600 at $2.95/W, 0% 25D) offsets ~$1,635/yr at 1,350 kWh/kW.

Distributed PV

### 8,752 Net-Metered Systems

82.708 MW residential PV (3.46% of customers) across 7 counties; state FEMA declarations (2015-2026): 8.

The Potomac Edison Company Reliability & Solar Offset Calculation

Backup_Energy = (307.5 min / 60) * 1.8 kW = 9.2 kWh/event | Solar_Offset = 10,800 kWh * $0.1514 = $1,635/yr

EIA-861 2025 Utility ID 15263: Rate=15.14 c/kWh, Cust=252,583, SAIDI=399.1 min, PV=8,752.

**Result:** 6.65 outage hrs/yr; 14.4 yr 8 kW cash payback (0% 25D).

## What Are the EIA-861 Filing Metrics for The Potomac Edison Company?

Complete Form EIA-861 filing summary for The Potomac Edison Company (ID 15263) covering sales, PV, and counties. Use these verified dataset benchmarks alongside a licensed electrician load calculation to compare residential upgrade bids with confidence.

Form EIA-861 2025 filing metrics for The Potomac Edison Company (Utility ID 15263).

| EIA Utility ID & BA Code | ID 15263 · PJM |
|---|---|
| State & Ownership Type | MD · Investor Owned |
| Retail Electricity Rates | 15.14 c/kWh Res · 7.76 c Comm · 4.03 c Ind |
| Avg Monthly Usage & Bill | 1,144.5 kWh/mo ($173.26/mo est.) |
| SAIDI (All Events w/ MED) | 399.1 min/yr (6.65 hrs/yr) |
| SAIDI (Without Major Events) | 173.8 min/yr (Storm share: 56.5%) |
| SAIFI & CAIDI (Per-Outage Avg) | 1.298 /yr · 307.5 min restore |
| Residential Net-Metered PV | 8,752 systems (82.708 MW) |
| Counties Served (Sample) | 7 counties (Allegany, Carroll, Frederick, Garrett, Howard, Montgomery, Washington) |

## Which Peer Electric Utilities Operate in MD?

Compare The Potomac Edison Company directly with Delmarva Power and nearby Maryland electric utilities by customer base. Compare thermal ratings, overcurrent protection caps, and continuous load headroom carefully before expanding an existing home service panel.

In-state EIA-861 peers ranked by customer base.

| Utility | Res Rate | SAIDI | Res PV | Customers |
|---|---|---|---|---|
| [**Delmarva Power**](https://epri-peac.com/utilities/md-delmarva-power-5027/) | 21.35 c | 114.0 min | 7,223 | 181,839 |
| [**Southern Maryland Elec Coop Inc**](https://epri-peac.com/utilities/md-southern-maryland-elec-coop-inc-17637/) | 16.4 c | 173.1 min | 9,514 | 162,860 |
| [**Choptank Electric Cooperative, Inc**](https://epri-peac.com/utilities/md-choptank-electric-cooperative-inc-3503/) | 17.11 c | 216.5 min | 1,412 | 50,981 |
| [**Constellation NewEnergy, Inc**](https://epri-peac.com/utilities/md-constellation-newenergy-inc-13374/) | 11.79 c | — | 0 | 44,070 |

What to Check & Best-Fit Scenarios

## What Should The Potomac Edison Company Customers Check Beyond Historical EIA-861 Averages?

Form EIA-861 data for The Potomac Edison Company (Investor Owned, MD) summarizes annual utility filings—confirm active rate riders and feeder reliability at your meter.

- Tariff structure differs: The Potomac Edison Company's 15.14 c/kWh blended residential rate in MD does not isolate peak TOU windows or fixed customer fees.
- Feeder variation: The Potomac Edison Company system-wide SAIDI averages rural and urban circuits across its MD territory or nearby Delmarva Power.

### The Potomac Edison Company Solar & Battery Evaluators

Compare your actual The Potomac Edison Company monthly kWh statement against 15.14 c/kWh and verify current export tariffs in MD.

### The Potomac Edison Company Outage & Generator Planners

Use The Potomac Edison Company's SAIDI history alongside NEC 705.12 120% busbar checks when sizing backup storage or transfer switches.

## Which Homeowner Electrical & Solar Questions Come Up Most Often?

Answers for The Potomac Edison Company (Maryland) customers grounded in 2025 Form EIA-861 filings and NEC 705.12 rules.

### What is The Potomac Edison Company's residential electricity rate and 2026 solar payback?

The Potomac Edison Company averages 15.14 c/kWh (-4.39 c/kWh vs Maryland average vs. Maryland). At 0% federal 25D credit in 2026, an 8 kW cash array offsets ~$1,635/yr (14.4-year payback).

### How reliable is The Potomac Edison Company compared to peer Maryland utilities?

The Potomac Edison Company logged 399.1 SAIDI outage minutes (6.65 hrs/yr, 56.5% storm-driven), making battery backup or a standby ATS worthwhile; compare rates and outage history directly with Delmarva Power (21.35 c/kWh) across Maryland.

### Which counties and customers does The Potomac Edison Company serve in Maryland?

EIA-861 filings list 252,583 customers across 7 counties including Allegany, Carroll, Frederick, with 8,752 net-metered residential solar installations. Review current municipal Authority Having Jurisdiction (AHJ) code amendments affecting The Potomac Edison Company.

## Related Pages

Explore Maryland energy benchmarks, Delmarva Power, county outage profiles, and NEC 705.12 tools alongside The Potomac Edison Company.

[Maryland State Energy Rates & Utilities](https://epri-peac.com/states/maryland/) [All Maryland County Power & Outage Profiles](https://epri-peac.com/counties/maryland/) [Check Solar 120% Busbar Rule (NEC 705.12)](https://epri-peac.com/tools/solar-busbar-120/) [All Indexed US Electric Utilities](https://epri-peac.com/utilities/)

## Sources

1. [Annual Electric Power Industry Report, Form EIA-861 (Reliability, Sales, Net Metering, Average Bill, Service Territory)](https://www.eia.gov/electricity/data/eia861/) — U.S. Energy Information Administration (EIA), 2025 Release (f8612025) (retrieved 2026-11-23)
2. [NFPA 70 National Electrical Code (Section Numbers & Standard Engineering Tables Only)](https://www.nfpa.org/codes-and-standards/nfpa-70-standard-development/70) — National Fire Protection Association (NFPA), 2020 / 2023 / 2026 Editions (retrieved 2026-11-23)
3. [Residential Clean Energy Credit (IRC Section 25D — Terminated After Dec. 31, 2025)](https://www.irs.gov/credits-deductions/residential-clean-energy-credit) — Internal Revenue Service (IRS), 2026 Guidance (P.L. 119-21) (retrieved 2026-11-23)

Solar & Backup Calculators

Evaluate 60 A hybrid battery ESS backfeed limits (NEC 705.12) and 2026 solar payback using 15.14 c/kWh rates.
[Check 120% Busbar Rule](https://epri-peac.com/tools/solar-busbar-120/) [View Battery & Generator Specs](https://epri-peac.com/ev-chargers/)