EIA-861 Grid Reliability & Net Metering

# CMS Electric Coop Inc (KS) — Grid Reliability & Solar Data

Filing: **Form EIA-861 (2025 Release)** Verified: **2026-11-26**

CMS Electric Coop Inc (EIA ID 2774, KS) serves 3,221 customers at 21.72 c/kWh (+7.28 c/kWh vs Kansas average) with no standalone IEEE SAIDI filing (10 counties served) with zero residential net-metered PV reported in 2025 filings. All figures reconcile directly against federal energy archives, state electrical licensing boards, California Energy Commission datasheets, and National Electrical Code engineering constants.

- **EIA Utility ID** : 2774

- **Res. Rate** : 21.72 c/kWh

- **SAIDI (All Events)** : Not reported in EIA-861

- **Net-Metered PV** : Unreported

Electric utility distribution substation transformers, ceramic insulators, and overhead feeder lines at dusk

## How Does CMS Electric Coop Inc Compare on Tariffs and Reliability?

How CMS Electric Coop Inc (Cooperative) performs across 10 counties on kWh rates and outage resilience. Homeowners and permit reviewers can filter tables below to benchmark specific ratings, wiring ages, and code allowances side by side.

Across 10 counties including Barber, Clark, Comanche, CMS Electric Coop Inc bills residential power at 21.72 c/kWh (+7.28 c/kWh vs Kansas average vs. Kansas), offsetting ~$2,346/yr on an 8 kW array compared to peer City of Chanute (KS) (14.56 c/kWh). With 3,221 customer accounts (Cooperative), 2025 Form EIA-861 shows CMS Electric Coop Inc did not file standalone IEEE SAIDI metrics in 2025 EIA-861 (state customer-weighted SAIDI is 192.8 min/yr), with zero residential net-metered PV reported in 2025 filings.

## Where Does CMS Electric Coop Inc Sit Across US Utility Rates?

National utility tariff curve marking CMS Electric Coop Inc at 21.72 c/kWh vs. 18.54 c/kWh US mean.

## How Does CMS Electric Coop Inc Rank Across Cost & Reliability?

Relative ranking of CMS Electric Coop Inc on residential electricity pricing and annual IEEE SAIDI outage duration. Use these verified dataset benchmarks alongside a licensed electrician load calculation to compare residential upgrade bids with confidence.

## What Do EIA-861 Benchmarks Show for CMS Electric Coop Inc?

Tariff rank, outage reliability metrics, and 2026 Post-25D solar payback figures for CMS Electric Coop Inc in Kansas.

Lowest Rate #1,833 / 1,989

### 21.72 c/kWh (+7.28 vs KS)

Commercial avg: 14.39 c/kWh; Industrial: 8.64 c/kWh; est. residential bill $143.70/mo.

State Reliability Context

### 192.8 min/yr (KS Avg)

Utility did not file separate IEEE SAIDI in 2025; Kansas customer-weighted SAIDI is 192.8 min/yr.

Post-25D Payback

### 10.1 Years @ 21.72 c/kWh

8 kW cash system ($23,600 at $2.95/W, 0% 25D) offsets ~$2,346/yr at 1,350 kWh/kW.

Service Territory

### 3,221 Customers · 10 Counties

Serves 10 counties including Barber, Clark, Comanche in Kansas; state FEMA declarations (2015-2026): 40.

CMS Electric Coop Inc Reliability & Solar Offset Calculation

Backup_Energy = (120.0 min / 60) * 1.8 kW = 3.6 kWh/event | Solar_Offset = 10,800 kWh * $0.2172 = $2,346/yr

EIA-861 2025 Utility ID 2774: Rate=21.72 c/kWh, Cust=3,221.

**Result:** 10.1 yr 8 kW cash payback at 21.72 c/kWh (0% 25D).

## What Are the EIA-861 Filing Metrics for CMS Electric Coop Inc?

Verified customer accounts, residential and commercial tariffs, and net-metering totals filed by CMS Electric Coop Inc. Always verify current state NEC adoption cycles, local utility interconnection tariffs, and panel busbar ratings before pulling project permits.

Form EIA-861 2025 filing metrics for CMS Electric Coop Inc (Utility ID 2774).

| EIA Utility ID & BA Code | ID 2774 · SWPP |
|---|---|
| State & Ownership Type | KS · Cooperative |
| Retail Electricity Rates | 21.72 c/kWh Res · 14.39 c Comm · 8.64 c Ind |
| Avg Monthly Usage & Bill | 661.7 kWh/mo ($143.70/mo est.) |
| Residential Net-Metered PV | Not reported in 2025 EIA-861 |
| Counties Served (Sample) | 10 counties (Barber, Clark, Comanche, Ford, Gray, Haskell, Kiowa, Meade, Seward, Stevens) |

## Which Peer Electric Utilities Operate in KS?

Nearby Kansas electric utilities of comparable customer size led by City of Chanute (KS) (14.56 c/kWh). Inspect manufacturer nameplate documentation, UL listing boundaries, and utility rate schedules closely before ordering electrical hardware.

In-state EIA-861 peers ranked by customer base.

| Utility | Res Rate | SAIDI | Res PV | Customers |
|---|---|---|---|---|
| [**City of Chanute (KS)**](https://epri-peac.com/utilities/ks-city-of-chanute-ks-3355/) | 14.56 c | — | 0 | 4,553 |
| [**City of Coffeyville - (KS)**](https://epri-peac.com/utilities/ks-city-of-coffeyville-ks-3892/) | 12.42 c | 45.4 min | 0 | 4,717 |
| [**Pioneer Electric Coop, Inc - (KS)**](https://epri-peac.com/utilities/ks-pioneer-electric-coop-inc-ks-15073/) | 11.85 c | 265.2 min | 27 | 5,038 |
| [**Tri-County Electric Coop, Inc (OK)**](https://epri-peac.com/utilities/ks-tri-county-electric-coop-inc-ok-19160/) | 16.34 c | — | 0 | 1,110 |

What to Check & Best-Fit Scenarios

## What Should CMS Electric Coop Inc Customers Check Beyond Historical EIA-861 Averages?

Form EIA-861 data for CMS Electric Coop Inc (Cooperative, KS) summarizes annual utility filings—confirm active rate riders and feeder reliability at your meter.

- Tariff structure differs: CMS Electric Coop Inc's 21.72 c/kWh blended residential rate in KS does not isolate peak TOU windows or fixed customer fees.
- Feeder variation: CMS Electric Coop Inc system-wide SAIDI averages rural and urban circuits across its KS territory or nearby City of Chanute (KS).

### CMS Electric Coop Inc Solar & Battery Evaluators

Compare your actual CMS Electric Coop Inc monthly kWh statement against 21.72 c/kWh and verify current export tariffs in KS.

### CMS Electric Coop Inc Outage & Generator Planners

Use CMS Electric Coop Inc's SAIDI history alongside NEC 705.12 120% busbar checks when sizing backup storage or transfer switches.

## Which Homeowner Electrical & Solar Questions Come Up Most Often?

Answers for CMS Electric Coop Inc (Kansas) customers grounded in 2025 Form EIA-861 filings and NEC 705.12 rules.

### What is CMS Electric Coop Inc's residential electricity rate and 2026 solar payback?

CMS Electric Coop Inc averages 21.72 c/kWh (+7.28 c/kWh vs Kansas average vs. Kansas). At 0% federal 25D credit in 2026, an 8 kW cash array offsets ~$2,346/yr (10.1-year payback).

### How reliable is CMS Electric Coop Inc compared to peer Kansas utilities?

CMS Electric Coop Inc did not file standalone IEEE SAIDI metrics in 2025 EIA-861 (state customer-weighted SAIDI is 192.8 min/yr); compare rates and outage history directly with City of Chanute (KS) (14.56 c/kWh) across Kansas.

### Which counties and customers does CMS Electric Coop Inc serve in Kansas?

EIA-861 filings list 3,221 customers across 10 counties including Barber, Clark, Comanche, with 0 net-metered residential solar installations. Review current municipal Authority Having Jurisdiction (AHJ) code amendments affecting CMS Electric Coop Inc.

## Related Pages

Explore Kansas energy benchmarks, City of Chanute (KS), county outage profiles, and NEC 705.12 tools alongside CMS Electric Coop Inc.

[Kansas State Energy Rates & Utilities](https://epri-peac.com/states/kansas/) [All Kansas County Power & Outage Profiles](https://epri-peac.com/counties/kansas/) [Check Solar 120% Busbar Rule (NEC 705.12)](https://epri-peac.com/tools/solar-busbar-120/) [All Indexed US Electric Utilities](https://epri-peac.com/utilities/)

## Sources

1. [Annual Electric Power Industry Report, Form EIA-861 (Reliability, Sales, Net Metering, Average Bill, Service Territory)](https://www.eia.gov/electricity/data/eia861/) — U.S. Energy Information Administration (EIA), 2025 Release (f8612025) (retrieved 2026-11-23)
2. [NFPA 70 National Electrical Code (Section Numbers & Standard Engineering Tables Only)](https://www.nfpa.org/codes-and-standards/nfpa-70-standard-development/70) — National Fire Protection Association (NFPA), 2020 / 2023 / 2026 Editions (retrieved 2026-11-23)
3. [Residential Clean Energy Credit (IRC Section 25D — Terminated After Dec. 31, 2025)](https://www.irs.gov/credits-deductions/residential-clean-energy-credit) — Internal Revenue Service (IRS), 2026 Guidance (P.L. 119-21) (retrieved 2026-11-23)

Solar & Backup Calculators

Evaluate 60 A hybrid battery ESS backfeed limits (NEC 705.12) and 2026 solar payback using 21.72 c/kWh rates.
[Check 120% Busbar Rule](https://epri-peac.com/tools/solar-busbar-120/) [View Battery & Generator Specs](https://epri-peac.com/ev-chargers/)