Filing: **Form EIA-861 (2025 Release)** Verified: **2026-11-26**

Avista Corp (EIA ID 20169, ID) serves 129,181 customers at 11.84 c/kWh (+0.01 c/kWh vs Idaho average) with 973.0 min/yr SAIDI (16.22 hrs/yr) with 827 net-metered residential solar systems (0.64% customer adoption). All figures reconcile directly against federal energy archives, state electrical licensing boards, California Energy Commission datasheets, and National Electrical Code engineering constants.

- **EIA Utility ID** : 20169

- **Res. Rate** : 11.84 c/kWh

- **SAIDI (All Events)** : 973.0 min/yr

- **Net-Metered PV** : 827 systems

Electric utility distribution substation transformers, ceramic insulators, and overhead feeder lines at dusk

## How Does Avista Corp Compare on Tariffs and Reliability?

Solar payback, residential tariff (11.84 c/kWh), and outage history inside Avista Corp territory. Homeowners and permit reviewers can filter tables below to benchmark specific ratings, wiring ages, and code allowances side by side.

Homeowners inside Avista Corp's Idaho footprint (9 counties including Benewah, Bonner, Clearwater) face 11.84 c/kWh benchmark pricing (-6.70 c/kWh vs US weighted mean). At 0% federal 25D credit in 2026, an 8 kW cash array ($23,600) pays back in 18.5 years. Reliability data logged 973.0 SAIDI outage minutes (16.22 hrs/yr, 78.6% storm-driven), making battery backup or a standby ATS worthwhile.

## Where Does Avista Corp Sit Across US Utility Rates?

Benchmarking Avista Corp's 11.84 c/kWh residential rate against 1,989 EIA-861 utilities. Always verify current state NEC adoption cycles, local utility interconnection tariffs, and panel busbar ratings before pulling project permits.

## How Does Avista Corp Rank Across Cost & Reliability?

Residential electricity cost and IEEE outage reliability percentiles for Avista Corp across Idaho utilities. Compare thermal ratings, overcurrent protection caps, and continuous load headroom carefully before expanding an existing home service panel.

## What Do EIA-861 Benchmarks Show for Avista Corp?

Key retail tariff, annual SAIDI outage, and distributed solar numbers reported by Avista Corp in 2025. Published percentiles compare local state, county, metro, and certified equipment metrics against nationwide residential electrical baselines.

Lowest Rate #368 / 1,989

### 11.84 c/kWh (+0.01 vs ID)

Commercial avg: 9.6 c/kWh; Industrial: 5.14 c/kWh; est. residential bill $106.63/mo.

Reliability #710 / 751

### 973.0 min/yr (16.22 hrs)

78.6% (765.0 min) from Major Event Days; avg restore 514.8 min (~15.4 kWh @ 1.8 kW).

Post-25D Payback

### 18.5 Years @ 11.84 c/kWh

8 kW cash system ($23,600 at $2.95/W, 0% 25D) offsets ~$1,279/yr at 1,350 kWh/kW.

Distributed PV

### 827 Net-Metered Systems

7.446 MW residential PV (0.64% of customers) across 9 counties; state FEMA declarations (2015-2026): 26.

Avista Corp Reliability & Solar Offset Calculation

Backup_Energy = (514.8 min / 60) * 1.8 kW = 15.4 kWh/event | Solar_Offset = 10,800 kWh * $0.1184 = $1,279/yr

EIA-861 2025 Utility ID 20169: Rate=11.84 c/kWh, Cust=129,181, SAIDI=973.0 min, PV=827.

**Result:** 16.22 outage hrs/yr; 18.5 yr 8 kW cash payback (0% 25D).

## What Are the EIA-861 Filing Metrics for Avista Corp?

2025 Form EIA-861 reliability, retail rate, and county territory data for Utility ID 20169. Inspect manufacturer nameplate documentation, UL listing boundaries, and utility rate schedules closely before ordering electrical hardware.

Form EIA-861 2025 filing metrics for Avista Corp (Utility ID 20169).

| EIA Utility ID & BA Code | ID 20169 · AVA |
|---|---|
| State & Ownership Type | ID · Investor Owned |
| Retail Electricity Rates | 11.84 c/kWh Res · 9.6 c Comm · 5.14 c Ind |
| Avg Monthly Usage & Bill | 900.3 kWh/mo ($106.63/mo est.) |
| SAIDI (All Events w/ MED) | 973.0 min/yr (16.22 hrs/yr) |
| SAIDI (Without Major Events) | 208.0 min/yr (Storm share: 78.6%) |
| SAIFI & CAIDI (Per-Outage Avg) | 1.89 /yr · 514.8 min restore |
| Residential Net-Metered PV | 827 systems (7.446 MW) |
| Counties Served (Sample) | 9 counties (Benewah, Bonner, Clearwater, Idaho, Kootenai, Latah, Lewis, Nez Perce, Shoshone) |

## Which Peer Electric Utilities Operate in ID?

Benchmark Avista Corp directly against PacifiCorp and peer Idaho retail electric power providers. Cross-check local Authority Having Jurisdiction amendments and serving utility net-metering terms before finalizing project sizing.

In-state EIA-861 peers ranked by customer base.

| Utility | Res Rate | SAIDI | Res PV | Customers |
|---|---|---|---|---|
| [**PacifiCorp**](https://epri-peac.com/utilities/id-pacificorp-14354/) | 13.53 c | 145.9 min | 3,589 | 75,599 |
| [**Kootenai Electric Cooperative**](https://epri-peac.com/utilities/id-kootenai-electric-cooperative-10454/) | 13.44 c | 368.9 min | 240 | 31,004 |
| [**City of Idaho Falls - (ID)**](https://epri-peac.com/utilities/id-city-of-idaho-falls-id-9187/) | 9.6 c | 50.6 min | 254 | 29,403 |
| [**Northern Lights, Inc**](https://epri-peac.com/utilities/id-northern-lights-inc-13758/) | 12.17 c | — | 0 | 18,172 |

What to Check & Best-Fit Scenarios

## What Should Avista Corp Customers Check Beyond Historical EIA-861 Averages?

Form EIA-861 data for Avista Corp (Investor Owned, ID) summarizes annual utility filings—confirm active rate riders and feeder reliability at your meter.

- Not a substitute for meter bills: tiered and seasonal kWh blocks inside Avista Corp (ID) shift real bills away from 11.84 c/kWh.
- Outage clustering: Major Event Days skew Avista Corp annual minutes differently than routine non-storm reliability.

### Avista Corp Solar & Battery Evaluators

Compare your actual Avista Corp monthly kWh statement against 11.84 c/kWh and verify current export tariffs in ID.

### Avista Corp Outage & Generator Planners

Use Avista Corp's SAIDI history alongside NEC 705.12 120% busbar checks when sizing backup storage or transfer switches.

## Which Homeowner Electrical & Solar Questions Come Up Most Often?

Answers for Avista Corp (Idaho) customers grounded in 2025 Form EIA-861 filings and NEC 705.12 rules. Every reported metric links directly to federal public records or state regulatory filings with zero paid contractor placements.

### What is Avista Corp's residential electricity rate and 2026 solar payback?

Avista Corp averages 11.84 c/kWh (+0.01 c/kWh vs Idaho average vs. Idaho). At 0% federal 25D credit in 2026, an 8 kW cash array offsets ~$1,279/yr (18.5-year payback).

### How reliable is Avista Corp compared to peer Idaho utilities?

Avista Corp logged 973.0 SAIDI outage minutes (16.22 hrs/yr, 78.6% storm-driven), making battery backup or a standby ATS worthwhile; compare rates and outage history directly with PacifiCorp (13.53 c/kWh) across Idaho.

### Which counties and customers does Avista Corp serve in Idaho?

EIA-861 filings list 129,181 customers across 9 counties including Benewah, Bonner, Clearwater, with 827 net-metered residential solar installations. Review current municipal Authority Having Jurisdiction (AHJ) code amendments affecting Avista Corp.

## Related Pages

Explore Idaho energy benchmarks, PacifiCorp, county outage profiles, and NEC 705.12 tools alongside Avista Corp. Data intervals combine current 2025 federal utility and BLS wage releases with verified state electrical board rosters.

[Idaho State Energy Rates & Utilities](https://epri-peac.com/states/idaho/) [All Idaho County Power & Outage Profiles](https://epri-peac.com/counties/idaho/) [Check Solar 120% Busbar Rule (NEC 705.12)](https://epri-peac.com/tools/solar-busbar-120/) [All Indexed US Electric Utilities](https://epri-peac.com/utilities/)

## Sources

1. [Annual Electric Power Industry Report, Form EIA-861 (Reliability, Sales, Net Metering, Average Bill, Service Territory)](https://www.eia.gov/electricity/data/eia861/) — U.S. Energy Information Administration (EIA), 2025 Release (f8612025) (retrieved 2026-11-23)
2. [NFPA 70 National Electrical Code (Section Numbers & Standard Engineering Tables Only)](https://www.nfpa.org/codes-and-standards/nfpa-70-standard-development/70) — National Fire Protection Association (NFPA), 2020 / 2023 / 2026 Editions (retrieved 2026-11-23)
3. [Residential Clean Energy Credit (IRC Section 25D — Terminated After Dec. 31, 2025)](https://www.irs.gov/credits-deductions/residential-clean-energy-credit) — Internal Revenue Service (IRS), 2026 Guidance (P.L. 119-21) (retrieved 2026-11-23)

Solar & Backup Calculators

Evaluate 60 A hybrid battery ESS backfeed limits (NEC 705.12) and 2026 solar payback using 11.84 c/kWh rates.
[Check 120% Busbar Rule](https://epri-peac.com/tools/solar-busbar-120/) [View Battery & Generator Specs](https://epri-peac.com/ev-chargers/)